Monday, November 26, 2018
Monday, November 19, 2018
Week 6: Weather Delay
The rain in the early part of the month has meant a two week delay to start framing. Hopefully the weather for the next two weeks is ok or we will be further delayed.
Monday, November 12, 2018
Week 5: Ready for framing
This week we finished all of the masonry odds and ends and passed the backfill inspection and now sit ready for framing.
Monday, November 5, 2018
Subscribe to:
Posts (Atom)
-
This week was waterproofing in the basement. The clients chose to do interior water proofing, as the water table and foundation indicate wa...
-
As Thom finished some of the brick patching in the front, Miguel finished up and managed to get the roof on before going on vacation for Ch...
-
George, Grant and I spent a few meetings this week going over the complex exterior detailing. This house will not be a simplified task of s...